MCS Ltd completed all MEP works to the new University of Coventry Campus located in Dagenham. The University took possession of the Grade II listed South Wing & Annex building with plans to expand.

MCS took the project on from a Stage 3 Design & further developed the scheme through to the construction stage.

The Project involved a complete refurbishment of the South Wing & Annex building, however with the Grade II listing of the building this made certain elements challenging. For example, the refurbishment of the existing luminaires, Installation of the new kitchen extract & works within the council chamber.

In addition to the project MCS carried out the supply & installation of the new commercial kitchen & servery.
Reference: Mark Overall (WDI)

Scope of services – Electrical Services

  • Submains
  • Distribution boards
  • General & emergency Lighting
  • Refurbishment of Grade 2 listed Luminaires
  • General & mechanical Power
  • Installation of a L3 category Fire alarm system
  • External lighting
  • Installation of a grade 3 intruder alarm system
  • Salto Access control system