MCS completed all MEP works to levels 6 to 10 (4 floors) at 10 Brock Street in London. Due to continual growth, Facebook took a new lease on level 10 carried out substantial refurbishment works to their existing floors at 10 Brock Street.

The project consisted of design, a validation of the existing electrical and mechanical services, decommissioning of existing electrical and mechanical services, provision and installation of a new, underfloor power installation, lighting installation, provision for a full AV installation, VRF system, sprinkler system, ventilation, BMS installation and commissioning.

MCS Ltd completed this work within a 12 week programme with all 4 floors working concurrently.

Scope of services

Electrical Services

  • New Distribution boards
  • General & emergency Lighting
  • General Power
  • Underfloor busbar installation
  • Mechanical Power
  • Installation and modification of existing Fire alarm system
  • AV and Data containment
  • Security Containment

Mechanical Services

  • Modification of the existing LTHW System
  • Re-configuration of the Building Management System
  • Installation of Kitchen Extract system
  • Installation of the new Domestic services
  • Domestic services to the new Kitchen
  • New installations and modifications to existing heating and chilled pipework.
  • Modification and rectification of existing landlord smoke damper system
  • Landlord and base build remedial work