MCS Ltd have been appointed for the design and installation of the mechanical works at Windmill Park in Swindon. This project includes the mechanical and public health installation to the South Wing of RWE’s head office.

The project consisted of full mechanical design from stage 3, provision and installation of a new four pipe fan coil VRF system, ventilation, CRAC package for critical comms rooms, new chiller plant and base build mechanical services, complete BMS installations and commissioning. This project is programmed for completion in 22 weeks.

Scope of work

Mechanical Services

  • Design from stage 3
  • Co-ordination
  • Four Pipe Fan Coil Unit Project
  • Heating pipework
  • Chilled pipework
  • Heating
  • Ventilation
  • Ductwork
  • Disposal Installations
  • BMS
  • Validation
  • Pre-contract water analysis
  • Decommissioning
  • Commissioning
  • Flushing
  • Balancing